How Long Does It Take to Paint a House in the Tri-Cities Area?
Quick answer: A whole-home interior repaint takes 3 days to 3 weeks depending on size and finish level. A single room takes 1 to 3 days. Exterior painting takes 3 days to 2 weeks and depends on weather. Kitchen cabinet refinishing takes 4 days to 2 weeks. Staircase and millwork staining takes 2 days to 2 weeks.

Price is the first question people ask me. This is the second, and it is usually the one they actually care more about.
Nobody enjoys having their house occupied. You want to know how many mornings you will be stepping around drop sheets, how long the spare room will be stacked with furniture, and when you get your kitchen back. Those are reasonable things to want a straight answer on.
So here is the real breakdown, by project type, with what happens on each day. These are our actual schedules in Kitchener, Waterloo, and Cambridge, not optimistic sales numbers.
Quick Timeline Summary
Project | Timeline |
Single room or accent wall | 1 to 3 days |
Whole-home interior, small home | 3 to 5 days |
Whole-home interior, mid-size home | 1 to 2 weeks |
Whole-home interior, large or sprayed | 2 to 3 weeks |
Exterior, small or single-storey | 3 to 4 days |
Exterior, two-storey | about 1 week |
Exterior, large or custom | 1 to 2 weeks |
Kitchen cabinet refinishing | 4 days to 2 weeks |
Staircase and millwork staining | 2 days to 2 weeks |
Commercial, single suite | 2 to 5 days |
Commercial, multi-room facility | 1 to 3 weeks |
How Long Does It Take to Paint a Whole House Interior?
Between 3 days and 3 weeks. Home size is the main driver, and how much beyond the walls you include is the second.
Small home, walls only: 3 to 5 days
Homes under 1,500 sq ft.
Day 1: Furniture moved and protected, floors covered, surfaces cleaned and lightly sanded, minor patching and nail-hole filling, caulking.
Days 2 to 3: First and second coats on walls, working room to room.
Day 4 or 5: Touch-ups, final inspection, walkthrough with you, and full cleanup.
Mid-size home with trim and ceilings: 1 to 2 weeks
Homes 1,500 to 2,800 sq ft.
Days 1 to 2: Full prep. Furniture moved and protected room by room, patching, sanding, filling, and a primer coat over every repaired area.
Days 3 to 4: Ceilings.
Days 5 to 7: Walls, two coats, room by room.
Days 8 to 9: Baseboards, door casing, and interior doors.
Day 10: Touch-ups, walkthrough, cleanup.
This is where most of our residential work lands.
Large or custom home with sprayed finish: 2 to 3 weeks
Homes 2,800 sq ft and up.
Add several days of masking and containment to the front of the schedule. Spraying itself is fast. Masking a house so that overspray goes nowhere it should not is not, and it is the difference between a furniture-grade finish and a problem.
Days 1 to 4: Full prep plus superior masking and site containment.
Days 5 to 12: Sprayed application on walls, ceilings, millwork, and doors, with multi-coat product build.
Days 13 to 15: High-ceiling and feature areas, detail work, touch-ups.
Final day: Walkthrough and cleanup.
How Long Does It Take to Paint One Room?
1 to 3 days.
1 day for a standard room in one colour, two coats, with cleaning, minor patching, caulking, and basic masking.
1 to 2 days if you add a feature wall, the ceiling, and touched-up baseboards and casing, with a full furniture move and protect.
2 to 3 days for a sprayed finish on trim, doors, and millwork with a premium multi-coat build, or specialty work like a coffered ceiling.
A single room is the least disruptive project we do, and it is a reasonable way to see how a company works before handing them the whole house.
How Long Does Exterior Painting Take?
3 days to 2 weeks, and weather is a genuine variable rather than an excuse.
Scope | Timeline |
Small or single-storey, one colour | 3 to 4 days |
Two-storey with trim and accent colours | about 1 week |
Large or custom with extensive wood repair | 1 to 2 weeks |
A typical two-storey week looks like this:
Day 1: Pressure washing to remove dirt, mildew, and chalking. Then the surfaces need to dry properly before anything else happens.
Days 2 to 3: Scraping, sanding, spot priming problem areas, caulking around windows, doors, and trim, and any minor wood repair.
Days 4 to 5: Body coats.
Day 6: Trim and accent colours, doors.
Day 7: Detail work, touch-ups, walkthrough, cleanup.
About weather. We stop when conditions are wrong. Coating a damp surface or working in poor conditions compromises adhesion and cure, and no schedule is worth a finish that fails in two years. We build buffer into every exterior timeline and we tell you as the forecast changes rather than leaving you guessing. Our exterior season runs March through October.
How Long Does Kitchen Cabinet Refinishing Take?
4 days to 2 weeks. Door and drawer count drives it, and so does the coating system.
Scope | Timeline |
Up to 15 doors and drawers, one-component coating | 4 to 6 days |
16 to 35 doors and drawers, island included | 6 to 9 days |
Two-component system, off-site booth finishing, interiors and built-ins | 10 to 14 days |
What happens when:
Day 1: Hardware removed and labelled, doors and drawer fronts taken off and moved to the spray area, cabinets degreased and deglossed.
Days 2 to 3: Scuff sanding for adhesion, wood fill and repair, masking the kitchen for in-place spraying.
Days 3 to 6: Boxes and face frames sprayed in place. Doors and drawer fronts sprayed separately, either on site or in an off-site booth on larger projects.
Remaining days: Cure time, then reinstallation of doors, drawers, and hardware, followed by final inspection.
Cure time is not padding. This is the part people are most tempted to rush and the part that punishes you for it. A cabinet finish that goes back on before it has hardened will mark the first time someone closes a door with a fingernail. On two-component systems we wait, and the wait is why the finish survives a decade of daily use.
Can you use your kitchen? Partly. Doors and drawer fronts come off early, so you will have open shelving for most of the project, but counters, sink, and appliances stay usable throughout. We give you a day-by-day outline before we start so you can plan around it.

How Long Does Staircase and Millwork Staining Take?
2 days to 2 weeks.
2 to 3 days for a small staircase of eight to ten stairs, or a standalone piece like a mantel, sanded, stained, and clear-coated.
4 to 7 days for a full staircase including stringers, risers, treads, and handrail, with a two-coat topcoat for high-traffic durability.
1 to 2 weeks for extended millwork including beams, banisters, and built-ins with a multi-coat furniture-grade build.
One thing worth planning for. A staircase under refinishing is a staircase you cannot use for stretches of the project. On a two-storey home with a single staircase, we sequence the work so you always have a route, but it takes coordination and it is worth talking through before we start rather than discovering it on day two.
How Long Does Commercial Painting Take?
2 days to 6 weeks, and access matters as much as square footage.
Scope | Timeline |
Single space or small suite | 2 to 5 days |
Multi-room or multi-suite facility | 1 to 3 weeks |
Large institutional or municipal building | 3 to 6 weeks |
Much of this work happens after hours or on weekends so operations keep running. That protects your business but it stretches the calendar, because a job with a six-hour nightly window takes more calendar days than the same job with full daytime access. We plan the sequence around your hours and tell you honestly what each option does to the schedule.
What Makes a Painting Project Take Longer?
Surface condition. This is the big one. Extensive patching, plaster repair, or layered old paint that needs sanding adds days before any colour goes on. Older homes near Victoria Park in Kitchener, Uptown Waterloo, and downtown Galt frequently need more prep time than newer builds.
Spraying versus brushing. Spraying is faster to apply and much slower to prepare. Masking and containment can add several days to a large project.
Colour changes. Dark to light needs full-coverage priming and additional coats.
High ceilings. Vaulted areas and two-storey foyers need staging, which slows everything down.
Weather. Exterior only, but it is real. We build buffer in rather than promising dates we cannot control.
Occupied spaces. Working around your life, your pets, or your business is slower than working in an empty house, and worth it.
Why Winter Is the Best Time to Book Interior Work
Here is something most homeowners do not think about.
Everyone calls us in spring. From March onward our calendar tightens fast, exterior season opens, and lead times stretch. Which means the exact same interior project you are considering will be scheduled sooner, and with more flexibility on your preferred dates, if you book it between November and February.
The old objection to winter interior painting was fumes and ventilation. Modern low-VOC products have largely removed that. You are not opening every window in January to survive the smell of your own hallway.
If you want the shortest wait and the most say in your dates, winter is genuinely the smartest time to do interior work in this region. Exterior is a different story, and for that you want to be booking in late winter for a spring or summer slot, because those fill first.
Frequently Asked Questions
How long does it take to paint a 2,000 sq ft house?
A 2,000 sq ft home falls in the mid-size range, so 1 to 2 weeks for a full interior including ceilings, baseboards, casing, and doors. Walls only would be closer to 3 to 5 days.
Can I live in my house while it is being painted?
Yes, and most of our clients do. We work room by room and contain dust so the whole house is never out of commission at once. For large sprayed projects we will talk through timing and containment beforehand so you can decide what is comfortable.
How long does paint take to dry between coats?
Most modern interior products are recoatable within 2 to 4 hours, though full cure takes considerably longer. Cabinets and high-durability coatings need more time, which is why cabinet projects run longer than the application days alone would suggest.
Will bad weather delay my exterior painting?
It can, and we plan for it. We stop when conditions compromise adhesion or cure, build buffer into every exterior schedule, and keep you updated as the forecast changes rather than leaving you guessing.
How far in advance should I book?
For interior work, 2 to 4 weeks is typical, and shorter in winter. Exterior projects need more lead time because our season runs March through October and spring slots fill early, so booking in late winter is worth it if you have a date in mind.
Do you work weekends or evenings?
For commercial and property maintenance projects, regularly, because that is often the only way to avoid disrupting operations. For residential work we generally keep to standard hours out of respect for you and your neighbours, but we will discuss it if your situation calls for something different.
Want a Real Schedule for Your Project?
Every timeline above assumes an average project. Yours has its own surfaces, its own scope, and its own constraints.
Book a walkthrough and we will give you a realistic schedule alongside your written quote, within 24 to 48 hours. If something shifts once we are underway, you will hear it from us before it affects you.